Prepare a trench for laying cables from DC and AC distribution box safely. The
suggested width of trench is 250mm (shaded area in Figure 3-2) and the
suggested depth is depended on user.
Prior to unpacking the system, make sure that you read and understand all
environmental and space requirements.
3.2 Preparing the Installation Site
3.2.1 Dimensions of trench
Figure 3-2 : Trench Dimensions
Build an installation base using the dimensions from the following illustration.
The width and depth of the metal base should not be smaller than the inverter,
and make sure the base can hold at least the weight of the inverter.
3.2.2 Dimensions & Characteristics of the base
Figure 3-3 : Installation Base Dimensions
270 60
unit: mm
16
14
90
950
770
90
170 590
2100
590
9090
580
Mounting Hole
unit: mm
18