72 8-10 kVA, 50/60 Hz (1-phase input) &
8-15 kVA, 50/60 Hz (3-phase input)
P-164000341
User's Guide Revision 1
TC Module Cable B Cable D Cable E
24 kVA 10 mm² 16 mm² (10 mm²)*
30 kVA 16 mm² 16 mm² (16 mm²)*
36 kVA 16 mm² 16 mm² -
45 kVA 35 mm² 16 mm² -
Table 10-2: Minimum cable and fuse rating for the different parallel system with installation
procedure C * (system bypass not allowed)
NOTE
Protection fuses need to be used for load cabling if manufacturers Tie Cabinet (or similar) not
used.
Required parallel system wiring length should be in accordance with the following rule, as referenced
to the diagram below to ensure approximately equal current sharing when in static bypass mode (see
Figure below:
Total length of 1A + 1B
= Total length of 2A + 2B
= Total length of 3A + 3B
= Total length of 4A + 4B
This rule has a tolerance of approximately ± 10% for the combined input and output wire lengths. If
installing only two UPS modules, this requirement is no longer required as each UPS is capable of
supporting the full bypass requirement. However, this would preclude future expansion.