Checks and Maintenance
76
Platinous User’s Manual
7.1 Check and Maintenance Lists
Check List
For an explanation on each check item, See “Checks” on page 77. If any of the following checks result in
problems, contact the place of purchase or Espec North America.
Maintenance List
For an explanation on each maintenance item, See “Maintenance” on page 77.
*Not necessary with temperature-only chambers
** Optional equipment
TABLE 7.14.
CHECK LIST
Check Item When to Check
Main Power Breaker Once Monthly
Overheat Protector Trip Test
Before long test runs
Before unmanned tests
Water Level Check for Humidifying Tray
Humidifying Tray Water Level Regulator
Once every 3 months
After moving chamber (See “Water Level
Check (ESL, ESX models only)” on
page 46.
TABLE 7.15. MAINTENANCE LIST
Maintenance Item When to Perform
Condenser Cleaning Once Monthly
Water Filter Cleaning* Once Monthly
Humidifying Tray Cleaning* Once Monthly
Humidifier Atomizing Nozzle Manual
Clean-Out Plunger**
Before/After Each Test
Humidifier Atomizing Nozzle Disassembly
& Cleaning**
Once Monthly
Test Area Cleaning Before Every Test
Electrical Compartment and Water Cir-
cuit Compartment Cleaning
Once Yearly
Take-Down Before Long Periods of Disuse

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ESPEC Platinous ESL-4C Series and is the answer not in the manual?

ESPEC Platinous ESL-4C Series Specifications

General IconGeneral
BrandESPEC
ModelPlatinous ESL-4C Series
CategoryClimate chamber
LanguageEnglish

Related product manuals