Installation
5 Commissioning and Trial Run
5.1 Check before startup
For safety of users and unit, the unit must be started up for check before debugging. The procedures
are as below:
The following items shall be performed by qualified repair persons.
Confirm together with the sales engineer, dealer, installing contractor and customers for the following items finished or to
be finished.
No.
Confirmation of Installation
1
If the contents of Application for Installation of this Unit by Installer are real. If not, debugging will be
refused.
2
Is there written notice in which amendment items are shown in respect of unqualified installation?
3
Are Application for Installation and Debugging list filed together?
No.
Pre-check
1
Is appearance of the unit and internal pipeline system ok during conveying, carrying or installation?
2
Check the accessories attached with the unit for quantity, package and so on.
3
Make sure there is drawings in terms of electricity, control, design of pipeline and so on.
4
Check if installation of the unit is stable enough and there is enough space for operation and repair.
5
Completely test refrigerant pressure of each unit and perform leakage detection of the unit.
6
Is the water tank installed stably and are supports secure when the water tank is full?
7
Are heat insulating measures for the water tank, outlet/inlet pipes and water replenishing pipe proper?
8
Are the nilometer of water tank, water temperature indicator, controller, manometer, pressure relief
valve and automatic discharge valve etc. installed and operated properly?
9
Does power supply accord with the nameplate? Do power cords conform to applicable requirements?
10
Is power supply and control wiring connected properly according to wiring diagram? Is earthing safe? Is
each terminal stable?
11
Are connection pipe, water pump, manometer, thermometer, valve etc. are installed properly?
12
Is each valve in the system open or closed according to requirements?
13
Confirm that the customers and inspection personnel of Part A are at site.
14
Is Installation Check-up Table completed and signed by the installation contractor?
Attention: If there is any item marked with ×, please notify the contractor. Items listed above are just for reference.
Confirmed Items after
pre-checking
General Evaluation: Debugging □ Amendment □
Judge the following items (if there is not any filling, qualification will be regarded.)
a: Power supply and electric control system b: Loading calculation
c: Heating problems of Unit d: Noise problem
e: Pipeline problem f: Others

Table of Contents

Other manuals for Gree VERSATI III Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Gree VERSATI III Series and is the answer not in the manual?

Gree VERSATI III Series Specifications

General IconGeneral
TypeAir to Water Heat Pump
SeriesVERSATI III
RefrigerantR32
Operating Temperature Range (Cooling)10°C to 48°C
Heating Capacity4.0 - 16.0 kW
Cooling Capacity4.0 - 14.0 kW
COPUp to 4.5 (A7/W35)
EER3.2 - 4.3
Power Supply220-240V, 50Hz