NO TICE
The AUX. SWITCH needs to be turned on only when the system is powered on for
the rst time and needs to be turned o during subsequent operation.
Step 6 Set the parameters on the app or SmartLogger. For details, see 7.3
Commissioning the SUN2000 (Using the SmartLogger) or the
SmartLogger
User Manual
.
Figure 7-1 Power-on
----End
7.2 Commissioning Methods and Process
The SUN2000 can be commissioned on the SmartLogger WebUI or FusionSolar
app. You are advised to use the SmartLogger WebUI for deployment
commissioning and use the app for password resetting and alarm viewing.
SUN2000-(250KTL, 280KTL, 300KTL, 330KTL) Series
User Manual 7 Power-On and Commissioning
Issue 07 (2023-06-30) Copyright © Huawei Technologies Co., Ltd. 65

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei SUN2000-330KTL-H2 and is the answer not in the manual?

Huawei SUN2000-330KTL-H2 Specifications

General IconGeneral
BrandHuawei
ModelSUN2000-330KTL-H2
CategoryInverter
LanguageEnglish

Related product manuals