5.7.4 (Optional) Connecting the Power Grid Scheduling Signal
Cable
Procedure
Step 1 Connect the signal cable to the signal cable connector.
Figure 5-29 Connecting the cable
Step 2 Connect the signal cable connector to the COM port.
Figure 5-30 Securing the signal cable connector
----End
SUN2000-(20KTL, 29.9KTL, 30KTL, 36KTL, 40KTL)-
M3
User Manual 5 Electrical Connections
Issue 18 (2024-03-10) Copyright © Huawei Technologies Co., Ltd. 62

Table of Contents

Other manuals for Huawei SUN2000-40KTL-M3

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei SUN2000-40KTL-M3 and is the answer not in the manual?

Huawei SUN2000-40KTL-M3 Specifications

General IconGeneral
BrandHuawei
ModelSUN2000-40KTL-M3
CategoryInverter
LanguageEnglish

Related product manuals