Context
This section describes operations on a single 15 kVA/20 kVA UPS.
Procedure
Step 1 Install power cables.
Figure 5-1 15 kVA/20 kVA UPS wiring diagram (three-phase input three-phase
output, two power sources)
NO TE
For details about how to install cables for the single system, see the
UPS2000-G-(15 kVA–
20 kVA) Quick Guide
.
----End
5.2.2 Starting the UPS
CA UTION
The congured number of batteries on the LCD must match the actual number.
When the actual number changes, change the congured number. If the
congured number is less than the actual number, the battery lifespan is
shortened. If the congured number is greater than the actual number, battery
leakage may cause a re.
UPS2000-G- (6 kVA-20 kVA)
User Manual 5 Operations
Issue 18 (2021-07-16) Copyright © Huawei Technologies Co., Ltd. 88

Table of Contents

Other manuals for Huawei UPS2000-G-10KRTL

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei UPS2000-G-10KRTL and is the answer not in the manual?

Huawei UPS2000-G-10KRTL Specifications

General IconGeneral
BrandHuawei
ModelUPS2000-G-10KRTL
CategoryUPS
LanguageEnglish

Related product manuals