134 HyPrecision Predictive waterjet pump Operator Manual 810120
5 – Preventive maintenance
Preventive maintenance
The pump is ready for operation.
Stage 5: Turn On the Cutting Head
Turn On the Cutting Head flashes on the screen at 1-second intervals.
1. Move the cutting head to a safe location on the table.
2. Turn
ON the cutting head.
3. Touch the
symbol.
Stage 6: Pressure Increasing
Pressure Increasing flashes on the screen at 1-second intervals.
The intensifier strokes to increase the water pressure in the system.
The target pressure increases to 1,380 bar (20,000 psi).
The target pressure increases to 2,070 bar (30,000 psi).
The target pressure increases to 2,760 bar (40,000 psi).
The target pressure increases to 3,450 bar (50,000 psi).
The target pressure increases to 4,140 bar (60,000 psi).
Stage 7: Close the Cutting Head
Turn Off the Cutting Head flashes on the PLC screen at 1-second
intervals.
1. Turn
OFF the cutting head.
2. Touch the
symbol.
Stage 8: Examine the Pump
Examine the Pump flashes on the screen at 1-second intervals.
1. Examine the pump for loose fittings or leaks.
2. Touch the
symbol.
The main motor turns off.
The primary operation screen opens.