4 Commissioning / 4.3 Commissioning after taking out of operation
© Copyright 2021 ABB. All rights reserved. HZTL4032_EN Rev.Q January 2021
4.3 Commissioning after taking out of operation
If present
u Remove cover plates (blind flanges) from the compressor casing, the gas inlet and the
gas outlet.
Version with compressor wheel cooling:
u Remove the locking screw on the cooling air connection and fit the cooling air line.
General
u Check the exhaust gas pipe before and after the turbine for combustion residues or wa-
ter residues and clean it. Remove any foreign objects that may be present.
u Check and clean filter silencer or air supply line, and remove any foreign objects that may
be present.
u Put engine-side oil circulation to the turbocharger into operation.
u Prepare the turbocharger for operation (see Checks before commissioning →41).
u The turbocharger is now ready for operation.
Page 43 / 194

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB A155-M66 and is the answer not in the manual?

ABB A155-M66 Specifications

General IconGeneral
BrandABB
ModelA155-M66
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals