07 COMMISSIONING
7) Wiring across shipping splits is completed according to the
instructions in the user manual (3BHS799208 E01 Rev E).
8) Ground cable of the drive is securely connected at both ends.
9) Cable armor and screens of power supply cables are connected
to PE ground busbar.
10) The transformer and motor cables are installed but the
conductors not connected at both ends (cables and drive must
be insulation resistance tested (Megger test)
before connection).
7.6.3 Door interlocking checklist
1) The release dial of the safety switches in the locked position.
7.6.4 Main circuit breaker (MCB)
1) MCB selected as per Main circuit breaker specification
(1)
2) High-voltage power connections completed
3) MCB is ready to be tested with drive
4) MCB protection relay settings are tested
5) Protection devices (eg, door locks) are tested and in operation.
6) Local operation of MCB is disabled.
7) Emergency-off loop is tested.
(1)
Pay attention to MCB opening time and installation of undervoltage coil or second
opening coil
7.6.5 Input transformer checklist
1) Grounding is completed
2) Transformer auxiliaries (eg, dehydrating breathers, cooling,
protection devices) are ready.
3) Protection devices are tested and in operation.
7.6.2 Electrical installation checklist (continued)

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB ACS5000 and is the answer not in the manual?

ABB ACS5000 Specifications

General IconGeneral
BrandABB
ModelACS5000
CategoryDC Drives
LanguageEnglish

Related product manuals