EasyManuals Logo
Home>ABB>DC Drives>ACS5000

ABB ACS5000 User Manual

ABB ACS5000
186 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #122 background imageLoading...
Page #122 background image
07 COMMISSIONING
3BHS799208 E01 REV E ACS5000 WATER-COOLED USER MANUAL 122/186
7.6.6 Motor checklist
1) Motor is installed, aligned and alignment protocol available.
2) Motor is not coupled to driven load.
3) Grounding is completed
4) Motor auxiliaries (eg, bearing lubrication) are ready
5) Control and monitoring signals are connected.
7.6.7 Insulation tests checklist
1) Insulation of the cables to input transformer, from input
transformer to drive and from drive to motor is tested, and
measured values within required limits.
2) Test report is available
If the commissioning personnel carry out the test, an additional
day per drive-motor combination must be reserved. After the
test, the mains cables can be connected, except at the drive end.
Test must comply with the specification.
7.6.8 Power checklist
1) Medium voltage available for startup of drive.
2) Low voltage is available for startup of drive.
7.6.9 Miscellaneous checklist
1) Sufficient number and correct type of spare parts available
2) Sufficient quantity of deionized water according is available.
(see Appendix C Mechanical drawings).
3) Air conditioning of drive room ready for load run of drive
4) Optional equipment (eg, chiller) ready

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB ACS5000 and is the answer not in the manual?

ABB ACS5000 Specifications

General IconGeneral
BrandABB
ModelACS5000
CategoryDC Drives
LanguageEnglish

Related product manuals