Production Setup and Testing
i3070 Series 5i Help 4-3
Production Testing
1 On the LCD touch panel, select Production mode.
2 Launch the Medalist i3070 software.
3 Load and run the testplan.
• When the testplan starts, commumication is established between the
controller and PLC.
• Settings are verified and the fixture ID is read.
• The Press is initialized.
• On the touch panel, Production mode is automatically set to Auto and
the system is ready to receive a board and begin testing.
Use the Engineer Test Interface for test debugging when needed.
Using the Break key on the keyboard will stop the testplan. In case communication with
the controller is lost, press and hold Stop on the LCD touch panel to stop the testplan
running.