46 Rockwell Automation Publication 6000-IN006F-EN-P - March 2018
Appendix A Pre-Commissioning
Pre-Commissioning Checklist
Once all points of the checklist are complete, initial each check box and provide
the date. Photocopy the checklist and fax the copy to the Rockwell Automation
Start-up Manager, along with the planned start-up date. Upon receiving this
checklist, the Project Manager will contact the site to finalize arrangements for a
start-up engineer to travel to the site at your convenience.
Please print the following information:
Table 7 - Receiving and Unpacking:
Table 8 - Installation and Mounting:
Table 9 - Safety:
Name: Date:
Company:
Phone: Pages:
Fax:
Drive Serial Number:
Rockwell Automation Service Engineer Requested (YES/NO):
Scheduled Commissioning Date:
Initials Date Check
The drives have been checked for shipping damage upon receiving.
After unpacking, the item(s) received are verified against the bill of materials.
Any claims for breakage or damage, whether concealed or obvious, are made to
the carrier by the customer as soon as possible after receipt of shipment.
All packing material, wedges, or braces are removed from the drive.
Initials Date Check
The drive is securely fastened in an upright position, on a level surface.
The Isolation Transformer Cabinet, Power Module Cabinet, and Bypass Cabinet (if
applicable) are correctly installed.
Lifting Angles have been removed.
Bolts are inserted into original location on top of drive (prevent leakage of
cooling air).
All contactors and relays have been operated manually to verify free movement.
The back plates to the cabinets have been reinstalled.
Initials Date Check
The grounding of the drive should be in accordance with national and local
electrical codes.