5.3 Performance tests
Introduction
This section describes how to run performance tests. Performance tests should be run
before taking ÄKTA go into use, to check the functionality of the equipment. After instal-
lation of a standard equipped ÄKTA go instrument, the System test and Mixer test must
be run. Performance tests must also be run for all modules that have a corresponding
test in the software. For example, if you have the Fraction collector F9-R, the Fraction
collector F9-R test must be run, and if you have the Column Valve V9-C, the Column
valve V9-C test should be performed. The Pump test is a shorter test that can be run to
test the pump. This is recommended if the pump has been replaced or undergone
maintenance.
Details of the individual tests including purpose and required material are given in the
method notes for each test method.
The performance tests are always run without a column.
Note:
Procedure
Performance tests are provided with the instrument configuration in the UNICORN
software.
Follow the general steps below to run a performance test. Detailed requirements and
procedures are shown on the screen when starting the test.
ActionStep
In the System Control module, select System:Performance Test and Report.1
70 ÄKTA go Operating Instructions 29360951 AC
5 Prepare the system for a run
5.3 Performance tests

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE AKTA GO and is the answer not in the manual?

GE AKTA GO Specifications

General IconGeneral
BrandGE
ModelAKTA GO
CategoryLaboratory Equipment
LanguageEnglish

Related product manuals