GE LOGIQ V5/LOGIQ V3
D
IRECTION 5496012-100, REVISION 3 BASIC SERVICE MANUAL
Chapter 3 - System Setup 3 - 11
Section 3-5
Completing the Installation
3-5-1 Power On / Boot Up
NOTE: After turning off a system, wait at least ten seconds before turning it on again. The system may not be
able to boot if power is recycled too quickly.
3-5-1-1 Scanner Power On
When power is applied to the scanner, power is distributed to the Cooling Unit, Control Panel, LCD,
Peripherals and the Back-end Processor.
3-5-1-2 Turn on the system
Press the Power On/Off switch at the front of the system once.
When the Power On/Off switch on the Control Panel is pressed once, the Back-end Processor starts
and the software code is distributed to initiate the scanner.
No status messages are displayed during this process.
Figure 3-3 Power On/Off Switch