4 Pre-installation Checks
This chapter provides information and procedures to perform pre-installation checks of the QuickPanel
+
Operator
Interface. Before installing and using the QuickPanel
+
, complete the following procedures:
• Unpacking and Inspection
• Basic Setup
• Initial Startup
• Runtime Setup
• Firmware Updates
• Shutdown
4.1 Unpacking and Inspection
Upon receipt of the QuickPanel
+
Operator Interface, carefully inspect all shipping containers for damage. If any part of
the system is damaged, notify the carrier immediately. Save the damaged shipping container for inspection by the
carrier. It is the
consignee’s responsibility to register a claim with the carrier for damage incurred during shipment.
Note For phone numbers and email addresses, refer to the section, Contact Information.
After unpacking the unit, record all serial numbers. These are needed to contact Customer Care during the warranty
period. Save all shipping containers and packing material for future transport or shipping. Verify that all system
components have been received and agree with the order. If the system received does not agree with your order,
contact Customer Care.
Before initial powerup, inspect the unit for loose or damaged components. If damage is found (such as bent component
leads or loose components), contact GE Intelligent Platforms for additional instructions.
Caution
Do not apply power to the unit if it has visible damage. Applying power to a unit
with damaged components may cause additional damage.