Installation
Erection general instructions
GE Information07- 2016 L30- 002EN/03
1/2
Erection general instructions
Instructions
of environment
The table below gives the instructions of environment to respect for the erec-
tion :
Instruction Comment
A
Verify the Civil engineering work : dimensions,
levels of concrete pads (structure fixation), in
accordance with the tolerances given by Civil
work standards (refer to circuit- breaker out-
line).
B
Avoid any dust production and masonry work
during erection of the circuit- breaker.
Erection
instructions
The table below gives the instructions to respect for proper erection of the cir-
cuit- breaker :
Instruction Comment
1
Read all the “Installation” modules completely
before beginning erection works.
The erection instructions describe all the pro-
cedures to be carried out as well as their chrono-
logical order .
2
Handle sub- assemblies in a correct manner,
particularly insulators.
3
The shipping case should be open as required
during erection procedures.
CAUTION
: Respect sub- assemblies iden-
tification.
4
When shipping covers are removed, proceed to
the next assembly sequence in as short as pos-
sible time.
Store the shipping covers under shelter, for a
possible future use.
5
Respect references to other modules,
i.e. :“T ightening torques”.
Warning
No responsibility is taken over by Grid Solutions for damages and disturb-
ances resulting out of non- adherence to the “Installation” modules.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE SF6 and is the answer not in the manual?

GE SF6 Specifications

General IconGeneral
BrandGE
ModelSF6
CategoryCircuit breakers
LanguageEnglish

Related product manuals