Commissioning
Instruction manual 854 ATG Page 11
3 Commissioning
3.1 Checks before starting the commissioning
E
xamine the mechanical and electrical installation after the 854 ATG is installed on the tank.
Refer to the installation guide 854 Advanced Technology Gauge.
Check the correct orientation of the gauge with respect to the tank.
Check that the gauge is leveled within 2°.
Check that the O-ring and gaskets are supplied.
Check that the mains voltage selector of the 854 ATG indicates the local mains supply.
Check the connections of all electrical cabling.
Check the ground connection of the 854 ATG to the tank.
Check that non-used cable inlets are sealed with appropriate stopping plugs.
Close carefully all covers (mind the O-rings) before any electrical power is applied.
Caution
Keep screw thread from the compartment covers free from dirt.
Grease them lightly with an acid-free grease before closing the instrument.
When closing, turn the covers counter-clockwise until the thread clicks into place, then turn clockwise.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Honeywell 854 ATG Series and is the answer not in the manual?

Honeywell 854 ATG Series Specifications

General IconGeneral
BrandHoneywell
Model854 ATG Series
CategoryMeasuring Instruments
LanguageEnglish

Related product manuals