3.6.3 Removing the Server and Holding Rails
Step 1 Wear an ESD wrist strap or ESD gloves. For details, see 1 Safety Instructions.
Step 2 Power off the server. For details, see 4 Powering On and Off the Server.
Step 3 Disconnect all power cables and signal cables from the server.
Step 4 Remove the server.
1. Loosen the captive screws on the server panel using a screwdriver. See (1) in Figure
3-35.
Figure 3-35 Removing the server from the holding rails
2. Pull out the server along the guide rails away from the cabinet as far as the server will
go. See (2) in Figure 3-35.
3. Pull the release button upwards, and pull the server out. See (1) and (2) in Figure 3-36.
5288 V3 Server
User Guide
3 Installing and Removing the 5288 V3
Issue 26 (2018-11-19) Copyright © Huawei Technologies Co., Ltd. 84