NOTE
When installing the TFM, ensure that the side with pins on the connector faces the TFM to prevent
damage of the device due to reverse insertion of the connector.
Step 8 Install the riser card tray above the RAID controller card. For details, see 7.19 Removing the
Riser Card.
Step 9 Install the chassis cover. For details, see 7.12 Installing the Chassis Cover.
Step 10 Install the 5288 V3. For details, see 3.4 Installing the Server.
Step 11 Connect all internal cables such as power and network cables. For details, see 3.5 Connecting
External Cables.
Step 12 Power on the 5288 V3. For details, see 4.1 Powering On the Server.
----End
7.36 Installing the Supercapacitor (Standard RAID
Controller Card)
Install a supercapacitor to replace the original one.
When LSI SAS3108 or PM8060 RAID controller cards are configured, supercapacitors can be
configured to provide extra power.
Before installing a supercapacitor, power off the server. Pay attention to electrical safety.
Procedure
Step 1 Wear an ESD wrist strap. For details, see 1 Safety Instructions.
Step 2 Remove the supercapacitor to be replaced. For details, see 7.34 Removing the
Supercapacitor (Standard RAID Controller Card).
Step 3 Take the supercapacitor out of its ESD bag.
Step 4 Place the supercapacitor downwards and exert even force to install it in the tray. Ensure that
the supercapacitor is secured by the plastic latches. See step (1) in Figure 7-67 and Figure
7-68.
Step 5 Determine the position and chip model of the RAID controller card connected to the
supercapacitor to be installed.
If the chip model of the RAID controller card connected to the supercapacitor to be installed
is LSI SAS3108, install the trans flash module (TFM) first.
5288 V3 Server
User Guide
7 Replacing Parts
Issue 26 (2018-11-19) Copyright © Huawei Technologies Co., Ltd. 182