Commissioning
Before switching on
8
l 125
EDS700ACBA EN 5.1
8 Commissioning
) Note!
ƒ Please observe the general safety instructions ( 13).
ƒ Please observe the notes regarding residual hazards ( 18).
8.1 Before switching on
Prevent injury to persons and damage to property by checking the following before
switching on the mains voltage.
Check
ƒ the wiring for completeness.
ƒ for the absence of short circuits and/or earth faults.
ƒ for the correct covering of the DC−bus wiring.
ƒ the "EMERGENCY OFF" function of the entire system.
ƒ the motor circuit configuration (star/delta). It must be adapted to the output
voltage of the controller.
ƒ the in−phase connection of the motor (direction of rotation).
ƒ whether the drive mechanically can be disconnected from the machine for
commissioning.
} Danger!
High hazard potential during commissioning
Incorrect settings can cause unexpected and dangerous movements of the
motor and the equipment.
Possible consequences:
ƒ Damage to material assets
ƒ Injury to persons
Protective measures:
ƒ Clear hazard area
ƒ Observe safety instructions and safety distances
8.2 Quick commissioning
Quick commissioning is described in
ƒ the "Controller−based automation, EtherCAT" communication manual,
the chapter "Commissioning of i700 servo inverter".

Table of Contents

Other manuals for Lenze i700 Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Lenze i700 Series and is the answer not in the manual?

Lenze i700 Series Specifications

General IconGeneral
BrandLenze
Modeli700 Series
CategoryInverter
LanguageEnglish

Related product manuals