Swing-away lattice
3.4 Description of the rigging work
Lattice extension operating instructions 3 112 441 en 3 - 59
GMK 4100/4100-L/5095
11.01.2008
3.4.11 Establishing / undoing connections at the swing-away lattice
(A) – If section 1 and section 2 are folded on the side for transport, you only
need to establish and undo the connection on the left-hand side.
(B) – If only section 1 is folded on the side for transport and section 2 has
been removed for transport, you must establish and undo the connections
on both sides.
Section 1 and
section 2 installed
You can relieve the connecting points if necessary;
à p. 3 - 51.
(A) – Establishing the connection
The connection is established after slewing
section 2 in front of section 1.
• Pull the pins (1) out of the retaining sheet (3).
• Insert the pins (1) in the connecting points (2)
and secure them with retaining pins.
(B) – Undoing the connection
The connection is undone before section 2 is
folded onto the side of section 1.
• Remove the pins (1) from the connecting
points (2).
• Insert the pins (1) in the retaining sheet (3)
and secure them with retaining pins.
s
G
Risk of accidents due to section 2 swinging of its own accord
Always secure section 2 with a guide rope and only position the ladder on
the left-hand side of section 1. In this way you will prevent section 2 from
swinging around of its own accord and knocking you off the ladder.