Particle filter
Start guide
NOTE
There must be water in the climate system be-
fore the switch is set to " ".
1.
Set switch (SF1) on F1226 to position "".
2.
Follow the instructions in the display's start guide.
If the start guide does not start when you start the
F1226, start it manually in menu 5.7.
TIP
See page 30 for a more in-depth introduction
to the heat pump’s control system (operation,
menus etc.).
Commissioning
The first time the heat pump is started a start guide is
started. The start guide instructions state what needs to
carried out at the first start together with a run through
of the heat pump’s basic settings.
The start guide ensures that start-up is carried out cor-
rectly and cannot be bypassed.The start guide can be
started later in menu 5.7.
Caution
As long as the start guide is active, no function
in the installation will start automatically.
The guide will appear at each installation restart
until it is deselected on the last page.
Operation in the start guide
A. Page
Here you can see how far you have come in the start
guide.
Scroll between the pages of the start guide as follows:
1.
Turn the control knob until one of the arrows in the
top left corner (at the page number) has been
marked.
2.
Press the OK button to skip between the pages in
the start guide.
B. Name and menu number
Read what menu in the control system this page of the
start guide is based on. The digits in brackets refer to the
menu number in the control system.
If you want to read more about affected menus either
consult the help menu or read the user manual.
C. Option / setting
Make settings for the system here.
D. Help menu
In many menus there is a symbol that indicates that
extra help is available.
To access the help text:
1.
Use the control knob to select the help symbol.
2.
Press the OK button.
The help text often consists of several windows that you
can scroll between using the control knob.
NIBE F1226Chapter 6 | Commissioning and adjusting26