106
AC-SVX001A-EN
Ascend™™ Model ACR
Installation Completion Check
Sheet and Request for Trane
Service
IImmppoorrttaanntt:: A copy of this completed form must be
submitted to the Trane service agency that
will be responsible for the start-up of the
chiller. Start-up will NOT proceed unless
applicable items listed in this form have
been satisfactorily completed.
To:
Trane Service Office:
S.O. Number:
Serial Numbers:
Job/Project Name:
Address:
The following items
are being installed
and will be completed by:
IImmppoorrttaanntt:: Start-up must be performed by Trane or an
agent of Trane specifically authorized to
perform start-up and warranty of Trane®
products. Contractor shall provide Trane
(or an agent of Trane specifically
authorized to perform start-up) with notice
of the scheduled start-up at least two weeks
prior to the scheduled start-up.
IImmppoorrttaanntt:: IItt iiss rreeqquuiirreedd tthhaatt hheeaatteerrss aarree eenneerrggiizzeedd
ffoorr aa mmiinniimmuumm ooff 2244 hhoouurrss pprriioorr ttoo ssttaarrtt
uupp.. TThheerreeffoorree,, cchhiilllleerr sshhoouulldd hhaavvee ppoowweerr
ffoorr tthhiiss aammoouunntt ooff ttiimmee bbeeffoorree TTrraannee
SSeerrvviiccee aarrrriivveess ttoo ddoo ssttaarrtt--uupp..
Check boxes if the task is complete or if the answer is
“yes”.
1. CChhiilllleerr
☐ Installation meets foundation requirements.
☐ In place and piped.
☐ Isolation pads or elastomeric pads installed
(optional).
☐ For units with InvisiSound™ Ultimate Option
(model number digit 12 = 3), compressor
mounting bolts have been removed.
2. RReeffrriiggeerraanntt PPrreessssuurree CChheecckk
☐ PRIOR to water being pumped into system, use
gauges to verify positive pressure in the
evaporator and condenser. Lack of pressure
could indicate a system leak. When charging in
the factory, approximately 95% of the
refrigerant charge is isolated in the evaporator,
and the other 5% is contained in the condenser
and compressor. In the event that no pressure is
present, contact local Trane service.
NNoottee:: Verification must be done by gauges. Do NOT
rely only on values from unit transducers.
3. PPiippiinngg
☐ Water piping flushed before making final
connections to the system
Chilled water piping connected to:
☐ Evaporator
☐ Air handling unit
☐ Pumps
☐ Flow switch or flow proving device
installed (if not factory provided)
☐ Strainer installed and cleaned
☐ Water supply connected to filling system
☐ Does unit have freeze inhibitor? If unit has
freeze inhibitor:
☐ Verify type and concentration correct per
unit submittal
☐ Calculate and record freeze point of the
solution: __________
☐ Systems filled
☐ Pumps run, air bled from system
☐ Strainer installed and cleaned
☐ Relief valve ventilation piping installed (if
applicable)
4. FFllooww bbaallaanncciinngg vvaallvveess iinnssttaalllleedd
☐ Leaving chilled water
5. GGaauuggeess,, tthheerrmmoommeetteerrss,, aanndd aaiirr vveennttss
☐ Installed on both sides of evaporator
6. WWiirriinngg
☐ Wire size per submittal and NEC 310-16
☐ Full power available
☐ Interconnecting wiring, starter to panel (as
required)
☐ External interlocks (flow switch, pumps
auxiliary, etc.)
☐ Chilled water pump (connected and tested)
☐ 115 Vac power available for service tools
☐ All controls installed and connected
7. TTeessttiinngg
☐ Dry nitrogen available for pressure testing
☐ Trace gas amounts of R-134a available for leak
testing, if necessary
8. RReeffrriiggeerraanntt oonn jjoobb ssiittee ((iiff nniittrrooggeenn cchhaarrggee
ooppttiioonn,, mmooddeell nnuummbbeerr ddiiggiitt 1155 == 22,, iiss cchhoosseenn))
9. SSyysstteemmss ccaann bbee ooppeerraatteedd uunnddeerr llooaadd ccoonnddiittiioonnss
LLoogg aanndd CChheecckk SShheeeettss