10. HHeeaatteerrss
If unit was factory charged (model number digit
15 = 1), energize heaters for 24 hours prior to
start up.
IImmppoorrttaanntt:: IItt iiss rreeqquuiirreedd tthhaatt cchhiilllleerr hheeaatteerrss
aarree eenneerrggiizzeedd ffoorr aa mmiinniimmuumm ooff
2244 hhoouurrss pprriioorr ttoo ssttaarrtt uupp..
TThheerreeffoorree,, cchhiilllleerr sshhoouulldd hhaavvee
ppoowweerr ffoorr tthhiiss aammoouunntt ooff ttiimmee
bbeeffoorree TTrraannee SSeerrvviiccee aarrrriivveess ttoo ddoo
ssttaarrtt--uupp..
If unit has nitrogen charge (model number digit
15 = 2), contact Trane Service for unit charging
prior to start-up.
IImmppoorrttaanntt:: Do NOT apply shore power to unit with
nitrogen charge. Shore power will drive
EXV valves, inhibiting ability to
adequately vac and charge unit.
11. OOwwnneerr AAwwaarreenneessss
Does the owner have a copy of the MSDS for
refrigerant?
NNoottee:: Additional time required to properly complete
the start-up and commissioning, due to any
incompleteness of the installation, will be
invoiced at prevailing rates.
This is to certify that the Trane® equipment has been
properly and completely installed, and that the
applicable items listed above have been satisfactorily
completed.
Checklist
completed by:
________________________________
Signed:
________________________________
Date: ________________________________
In accordance with your quotation and our purchase
order number __________________, we will therefore
require the presence of Trane service on this site, for
the purpose of start-up and commissioning, by
__________________ (date).
NNoottee:: Minimum two-week advance notification is
required to allow scheduling of the chiller start-
up.
Additional Comments/Instructions:
NNoottee:: A copy of this completed from must be
submitted to the Trane Service Office that will be
responsible for start-up of chiller.
LLoogg aanndd CChheecckk SShheeeettss

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Trane Ascend ACR Series and is the answer not in the manual?

Trane Ascend ACR Series Specifications

General IconGeneral
BrandTrane
ModelAscend ACR Series
CategoryChiller
LanguageEnglish

Related product manuals