10 - SYSTEM START-UP
10.1 - Checks before system start-up
Before starting up the thermodynamic system, the complete
system, including the thermodynamic system, must be veried
against the installation drawings, dimensional drawings, system
piping and instrumentation diagrams and the wiring diagrams.
All measures must be taken to ensure that the pressure and
temperature limits, specically those listed on the unit nameplates,
are not exceeded during operation, maintenance and recycling.
Heat exchange fluid temperatures above the maximum
recommended can lead to an increase in the refrigerant pressure
and can cause a loss of refrigerant due to the relief valve discharge.
National regulations must be followed during these checks. If the
national regulation does not specify any details, refer to standard
EN 378 as follows:
External visual installation checks:
- Ensure that the machine is charged with refrigerant. Verify
on the unit name plate that the ‘uid transported’ is that
recommended for operation, and is not nitrogen.
- Compare the complete installation with the refrigeration
system and power circuit diagrams.
- Check that all documents provided by the manufacturer
(dimensional drawings, pipe and instrument diagram (PID),
declarations, etc.) to comply with the regulations are present.
If any documentation is missing, order a replacement.
- Make sure the environmental safety and protection devices
and arrangements provided by the manufacturer to comply
with the regulations are in place.
- Make sure all declarations of conformity for the pressure
containers, identication plates and documentation required
to comply with local regulations are present.
- Verify the free passage of access and safety routes.
- Comply with the instructions and directives to prevent the
deliberate release of refrigerant uids.
- Verify the installation of connections.
- Verify the supports and xing elements (materials, routing
and connection).
- Verify the quality of welds and other joints.
- Check the protection against mechanical damage.
- Check the protection against heat.
- Check the protection of moving parts.
- Verify the accessibility for maintenance or repair and to check
the piping.
- Verify the status of the valves.
- Verify the quality of the thermal insulation.
- Check the condition of 400 V cable insulation.
10.2 - Commissioning
Always ensure you have read and fully understood the operating
instructions for the units before starting up the unit, and ensure
the following precautions have been taken:
- Check the heat-transfer fluid circulation pumps, the air
handling equipment, and any other equipment connected to
the heat exchangers.
- Refer to the manufacturer’s instructions.
- Refer to the electrical diagram delivered with the unit.
- Ensure there are no refrigerant leaks. Check the tightening
of the fastening clips on all the pipes.
- Check the power supply at the main connection point and
the order of phases.
- For units without a factory-tted hydraulic module, heat
protections and connections related to the installation pump
are the responsibility of the installer.
- Check the operation of the crankcase oil heater, as well as
the operation of the compressor head heaters if necessary,
for six hours before the installation is started up.
- Open the suction shut-o valves on each circuit for the
corresponding units.
IMPORTANT:
Commissioning and start-up must be supervised by a
qualied engineer.
- The system must have a heat load and water owing in
the exchangers when it is started up and tested.
- All setpoint adjustments and control tests must be
carried out before the unit is started up.
- Refer to the Service guide.
Proceed with the unit commissioning.
Make sure all safety devices are operational, and especially
that the high pressure switches are engaged and that any
alarms have been cleared.
NOTE:
If the manufacturer's recommendations (system, water and
power connections) are not observed, no claims made under
the warranty will be accepted.
10.3 - Essential points to check
Compressors
Ensure that each compressor is rotating in the correct direction,
checking that the discharge temperature rises quickly, the high
pressure increases and the low pressure drops. If it is rotating in
the wrong direction, the electric power supply is incorrectly wired
(reversed phases). To ensure rotation in the correct direction, swap
two power supply phases.
- Check the compressor discharge temperature using a contact
sensor
- Check the input current; it should be normal
- Check all safety devices to make sure they operate correctly
Hydraulics
As the exact total system pressure drop is not known at start-up,
adjust the water ow rate with the control valve until the desired
nominal rate is obtained.
Please refer to the chapter "Nominal system water ow rate control
- Procedure for adjusting the ow rate" for the steps to follow.
In any case, the hydraulic circuit must be free from pollution
(removal of any solid particles in the circuit) before start-up: Please
refer to the chapter "Nominal system water ow rate control -
Procedure for cleaning the hydraulic circuit" for the steps to follow.
Refrigerant charge
Each unit is shipped with an exact charge of refrigerant and oil.
Check that there are no visible refrigerant or oil leaks:
- No apparent damage on the refrigerant circuit pipes (no
trauma, cracks, deformation)
- No traces of grease on the connections and refrigerant circuit
sensors
In case of doubt, use a refrigerant leak detection device suited to
the uid in the unit.
33