7.1.0.3 Space heang pipes connecon
The unit is factory supplied with two shut-o valves which have to be connected to the water inlet
/ outlet connecons. With these shut-o valves it is very praccal to connect the indoor unit to the
heang system by using the factory supplied gaskets just below the valves. Then, the space heang
installaon can be carried out.
Gaskets
Shut-o valves
7.1.0.4 Drain pipes connecon
For a correct drainage, connect the drain pipe for the safety valve to the general draining system.
NOTE
• The safety valve is acvated when water pressure reaches 3 bars.
• Drain taps must be provided at all low points of the installaon to permit complete drainage of
the circuit during servicing.