2-4
Installing the switch
Installation procedure
Installation procedure
The following steps summarize switch installation. The rest of this chapter provides
details on these steps.
1. Prepare the installation site (page 2-5). Ensure that the physical environment
into which you will install the switch is properly prepared. The environment
must have the correct network cabling ready to connect to the switch and have
an appropriate location for the switch. See page 2-5 for some installation
precautions.
2. Mount the switch (page 2-5). The PS1810-8G Switch is designed to be stacked
with an HP ProLiant MicroServer Gen8. You can mount the switch on a wall or,
under or on top of a horizontal surface. The PS1810-24G Switch can be mounted
in a 19-inch Telco rack; in an equipment cabinet, on a wall or; under or on top
of a horizontal surface.
3. Connect the network devices (page 2-14). Using the appropriate network
cables, connect the network devices to the switch ports.
4. Optional: Install the SFP transceivers for the PS1810-24G Switch (page 2-
14). The PS1810-24G Switch has two slots for installing SFP transceivers.
Depending on where you install the switch, it might be easier to install the SFPs
first. SFPs can be hot swapped - you can install or remove while the switch is
powered on.
5. Connect the switch to the AC power source. Once the switch is mounted and
connected to the network devices, plug it into the main power source.
At this point, your switch is fully installed. See the rest of this chapter if you need
detailed information about any of these installation steps.