Operator information
panel
Release tab
5. From the front of the server, carefully pull the assembly out of the server while
you move it slightly from side to side.
6. If you are instructed to return the operator information panel assembly, follow all
packaging instructions, and use any packaging materials for shipping that are
supplied to you.
Installing the operator information panel assembly
To install the operator information panel, complete the following steps.
1. Read the safety information that begins on page vii and “Installation guidelines”
on page 167.
2. From the front of the server, slide the operator information panel into the server
until it clicks into place.
3. Inside the server, connect the cable to the rear of the operator information panel
assembly.
Operator information
panel
Release tab
The following illustration shows the cable routing for the operator information
panel:
Note: The operation information panel cable should go in between the
Video/USB cable (on the bottom) and the CD/DVD cable (on the top) when all
three cables are installed in the server.
Chapter 5. Removing and replacing server components 241