Boom extension
4.2 Description of the rigging work
4 - 14 3 112 441 en Lattice extension operating instructions
GMK 4100/4100-L/5095
11.01.2008
Connection to
the swing-away
lattice
(A) – Establishing the connection
• Remove the long ends (2) from the holders (4)
in section 3.
• Lay the long ends (2) through section 3 as
far forward as possible to section 1.
• Remove the hoses (3) from the holder (1) in
section 1.
• Remove the protective caps and connect the
hoses (3) with the long ends (2).
• Secure the hose lines at the holder (4) in
section 3 to ensure they do not hang out
during operation.
(B) – Disconnecting the connection
• Disconnect the hoses (3) from the long ends (2).
• Close the short ends and the hoses with the protective caps.
• Secure the hoses (3) at the holder (1) in section 1.
• Lay the long ends (2) to the rear through section 3.
• Secure the long ends (2) to the holders (4) in section 3 to prevent them
from hanging out during transport.