Swing-away lattice
3.3 Rigging work checklists
3 - 16 3 112 441 en Lattice extension operating instructions
GMK 4100/4100-L/5095
11.01.2008
6. Fold out the run-up rail; à p. 3 - 36.
7. Secure the lattice extension with the guide rope;
à p. 3 - 27.
8. Only applies to rigging the 10 m (33 ft) swing-away lattice if only
section 1 is installed.
– Undo the connection between section 1 and the main boom in the
Rear area; à p. 3 - 46.
9. Only applies to rigging the 10 m (33 ft) swing-away lattice if section 2 is
also installed.
– Bring the connection in the
Middle area into the section 2 / main boom
position;
à p. 3 - 43.
– Establish the connection between section 2 and the main boom in
the
Rear area; à p. 3 - 45.
– Undo the connection between section 2 and section 1 in the
Rear
area;
à p. 3 - 48.
10. Only applies to rigging the 17 m (56 ft) swing-away lattice.
– Check whether the connection in the
Middle area is in the section 1 /
section 2
position; à p. 3 - 42.
– Check whether the connection between section 1 and section 2 in
the
Rear area has been established; à p. 3 - 48.
– Undo the connection between section 2 and the main boom in the
Rear area; à p. 3 - 45.
11. Swing the lattice extension onto the main boom head;
à p. 3 - 54.