Manitowoc Published 12-10-19, Control # 258-05 4-47
MLC90A-1/MLC100-1 OPERATOR MANUAL SETUP AND INSTALLATION
3
1
4
Handling Boom and Jib Sections
All boom sections have lifting lugs as shown in Figure 4-12
on page 4-20.
• Handle the boom sections with care to avoid damaging
the lacings and chords.
• Use synthetic lifting slings (crane owner furnished) to lift
the boom sections.
The jib sections do not have lifting lugs.
• Handle the jib sections with care to avoid damaging the
lacings and chords.
• Use synthetic lifting slings (crane owner furnished) to
handle the jib sections. Lift at the chords only. Never lift
at the lacings.
If wire rope or chain slings are used to handle the boom or jib
sections, install protective covering (such as sections of
rubber tire) between the slings and component being lifted.
WARNING
Falling Load Hazard!
The lifting lugs on each boom section are designed only
for lifting that section. Do not attempt to lift two or more
boom sections with the lifting lugs on one section. The
lifting lugs may break allowing the boom sections to fall.
Figure 4-30
Boom Handling with Equalizer Pinned to Boom Butt
See Boom Rigging Drawing

Table of Contents

Other manuals for Manitowoc MLC100-1

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc MLC100-1 and is the answer not in the manual?

Manitowoc MLC100-1 Specifications

General IconGeneral
BrandManitowoc
ModelMLC100-1
CategoryConstruction Equipment
LanguageEnglish

Related product manuals