4-41
SINUMERIK 802C
6FC5 597–3AA20–0BP2 (01.02)
Start-Up
4.1 General
Start-up requirements
S The following is required:
– User’s Guide: “Operation and Programming, SINUMERIK 802C”
– PC/PG (programming device) only for data saving and series start-up
– Toolbox on CD. The CD is either supplied with the control system or can be ordered
separately.
Contents: see also p. 1–11
S The mechanical and electrical installation of the equipment must be completed.
Note
Installation notes are to be found in Chapter LEERER MERKER.
S The control system with its components has powered up without errors.
Start-up sequence
The SINUMERIK 802C can be strated up as follows:
1. Check whether the ENC has powered up.
2. PLC start–up
3. Technology setting
4. Set general machine data.
5. Set axis/machine-specific machine data.
– Match encoder with spindle
– Match setpoint with spindle
6. Dry run for axes and spindle(s)
7. Drive optimization
8. Complete start–up, data saving
4