POWER TRIM AND TILT 9-9
REASSEMBLY
Reassembly is reverse of removal with special attention to fol-
lowing steps.
Ensure that the drive joint 1 is aligned and firmly inserted
into the gear pump assembly.
Fit O-ring 2 to PTT motor.
Check the level of PTT fluid contained in the pump & reser-
voir. If level is low, add recommended PTT fluid until level with
mating surface of PTT motor.
Install seal and reservoir, then tighten the two (2) screws to
specified torque.
Reservoir screw : 4.5 N
.
m (0.45 kg-m, 3.3 lb.-ft.)
!
Ensure that the faces of the PTT motor and reservoir are free
of dirt or debris.
When attaching the PTT motor to the pump & reservoir, en-
sure that the tip of armature shaft fits firmly into the drive
joint.
Pour recommended PTT fluid into reservoir until specified
level.
Carry out the air bleeding.
For air bleeding, see page 9-3.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Suzuki DF 25 and is the answer not in the manual?

Suzuki DF 25 Specifications

General IconGeneral
BrandSuzuki
ModelDF 25
CategoryOutboard Motor
LanguageEnglish

Related product manuals