2007.03.07Flow2 stairliftTab 04: Install, adjust and release
www.ThyssenKruppAccessibility.nl10
Preassembly
3. Check that the voltage is approximately 33 V and the connection is as indicated in the upper
parts of the figures.
4. Connect the building wires from the charging contacts to the transformer.
5. Choose a suitable position for the transformer and secure it with four screws and washers.
2.6 Positioning the rail
1. Check the adjustment positions 'X', 'Y' and 'Z' using the
installation drawing. The adjustment dimensions are
measured from the wall or a tread to the centre of the rail’s
pipe.
2. Check the gradient of the rail against the gradients shown on
the installation drawing.
3. Locate the rail in the optimum position.
4. Adjust the legs and brackets such that the rail is stable on the stairs. Insert one or more
spacers between the legs and the rail if so required.
2.7 Greasing the rail
1. Degrease the rail with degreaser if it is greasy.
2. For greasing, use 'Super Lube' grease and spread it on the
rail with a brush.
- Grease the bearing surfaces in the holes.
- Grease the support wheel running surface.
TIP
Instead of extending the mains cable you can also extend the building wire and then fix it
out of sight.
TIP
Remove the plug from the wall socket.
Fig. 2-13 Rail position
1
Z
Y
Fig. 2-14 Rack greasing points for
attention
1