2007.03.07Flow2 stairliftTab 04: Install, adjust and release
www.ThyssenKruppAccessibility.nl11
3Assembly
Fully assemble the lift. Do not yet secure the rail to the stairs.
For the 'commissioning' of the Flow2, the following procedure has been defined. It is extremely
important to actually perform all the steps in sequence.
Procedure:
1. Prepare the drive unit.
2. Preparing to drive onto the rail.
3. Driving onto the rail.
4. Registering the radio frequency equipment.
5. Preparing the drive unit for use.
6. Fitting the chair base on the drive unit.
7. Installing the rail.
3.1 Prepare the drive unit
Place the drive unit, in its packaging, at the location where it will be driven onto the rail.
This is done as follows:
1. Open the packaging.
2. Remove the top frame from the box and place it next to the driving-on point on the rail.
3. Lift the drive unit out of the box and place it on the top frame so that the drive unit is in the right
position to drive onto the rail.
CAUTION
It is possible that the entire unit becomes somewhat unstable. In that case secure the rail
temporarily (for example with glue clamps).
TIP
When the driving-on point is at the top of the stairs, the drive unit will have to be carried
to the top in its box. The other boxes can be unpacked downstairs. Bring the empty
packaging material back downstairs again. You will then be certain that you do not forget
anything or accidentally throw something away with the packaging.