Installing the G1330B Thermostat
Installing the G1330B Thermostat
1 Connect the pump outlet capillary to port 1 of the injection valve.
2 Connect column-compartment inlet capillary to port 6 of the injection valve.
3 Ensure that the waste tube is positioned inside the leak channel.
Figure 14 Hydraulic Connections
Stage 4: Installing the Sample Tray
1 Load the sample tray with sample vials as required.
2 Slide the sample tray into the thermostatted autosampler so that the rear of
the sample tray is seated firmly against the rear of the sample-tray area.
3 Press the front of the sample tray down to secure the tray in the autosampler.
If the tray pops out of its position the air channel adapter is not inserted
correctly.
To metering device
To column compartment
From pump
From needle seat
To waste
Plug
Column compartment
Pump
Waste tube in
Leak channel