December 2008 CSO-FN-BVD-051
2. General Site Requirements Checklist
Customer is aware that all installations are of a Non-Moveable configuration only, this includes equipment installed
on concrete floors
The person responsible for the network from an IT perspective will be present at the time of install.
Equipment will be delivered on ground floor (If no, please review Stair Climbing/Crane Check List below)
3. Stair Climbing / Crane Check List
Will the equipment be delivered to any location "other than" the street level floor? If the answer is no, no need to stair
climb. If the answer is yes, continue with this section.
Is there an elevator that will accommodate the weight and dimensions of the IOT and delivery personnel? If the
answer is yes, no need to stair climb. If the answer is no, please continue with this form. IOT weight = 2205 pounds or
1000 kg, IOT dimensions = 1220mm Width x 750mm Depth, x 971.5mm Height.
Is the staircase wide enough to accommodate the stair climber and the IOT or other modules? If the answer is yes,
continue with this form. If the answer is no, the IOT must be brought into the install location by crane. IOT
dimensions = 1220mm Width x 750mm Depth, x 971.5mm Height. Paper trays 1/2 module dimensions = 1063mm
Width x 762mm Depth x 971.5mm Height.
Are there any permanent overhead obstructions along the staircase? If the answer is no, continue with this form. If
the answer is yes, measure from the bottom of the obstruction to the corner of the step just below (where the riser
meets the tread). This measurement must allow clearance of the stair climber, the IOT or paper handler and blankets.
For the IOT, this measurement must measure 1220mm, plus allow for clearance between the top of the step to the
bottom of the obstruction. For the paper handler, this measurement must allow for clearance between the top of the
step and the bottom of the obstruction. If the measurement allows clearance, continue with this form. If the
measurement does not allow clearance, the IOT or paper handler must be brought into the install location by crane.
Can the doorways at the top and bottom of the staircase accommodate the dimensions of the IOT? If the answer is
yes, the equipment can be stair climbed. Please check the "stair climbing equipment required for delivery" box below.
If the answer is no, the doorways must be enlarged to allow for passage of the IOT or the paper handler or the
equipment must be brought into the install location by crane.
If after completing all the questions in this section, it is determined that the equipment can be stair climbed or
craned check the relevant box.
STAIRCLIMBING EQUIPMENT REQUIRED FOR
DELIVERY
CRANE EQUIPMENT REQUIRED FOR DELIVERY
4. Notes: Site Alteration / Furniture / Equipment Relocation
5. Required Service Coverage: