No Precondition for Installation Remarks
Yes
/ No
1 Installation / Service person/s is qualified
2 Installation / Service person/s carefully read and understood this manual
3 The room size is no smaller than the limit in this manual (min 7 m²)
4 Walls can handle the installation of indoor and outdoor unit
5 No disruption to the environment
6 There is no damage or leakage at the new AC components
7 The set of AC components is complete
8 Installation tools and equipment is prepared and in place
9 Power connection (socket) at the right place
10 Electrical installation is safe and according the local requirements
11 Installation area is well ventilated
12 There are no sources of ignition within the range of two metres
13 Warning signs are placed
14 Fire extinguisher is present
15 Other persons in the area are informed about the activities
16 Mobile phone is switched off
17 Power socket of installation tools are more than two metres away
18 HC leak detector is placed and in operation
Installation Check List
Carefully asses the local conditions and consider that all safety measures
are in place. Check the needs for installation in order to arrange a smooth
and uninterrupted work flow.
Remember, if you cannot work safe with HC refrigerants, don't do it!
In general, the GREE Hydrocarbon R-290 AC– Split System must be set
up and configured to original factory specifications and tolerances!