Planning Considerations
Specific Considerations for the 3500-PoE Switches
Planning Considerations
Specific Considerations for the 3500-PoE
Switches
The following is an example list of considerations during the planning phase
specific to the 3500-PoE Switches:
What if power is lost to the switch?
Power for the switch to operate (system power)
Power for PoE devices
Which devices to plug into which ports and with what priorities?
Port prioritization
Port priority class
Reserve watts
Total watts available (398)
Which bank of 24 ports will be used?
Will load balancing be used?
Will any mini-GBICs be used and in what ports?
Should the 620 RPS/EPS be plugged into a different power source than
the switch it is going to back up.

Table of Contents

Other manuals for HP PROCURVE 2520

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the HP PROCURVE 2520 and is the answer not in the manual?

HP PROCURVE 2520 Specifications

General IconGeneral
BrandHP
ModelPROCURVE 2520
CategorySoftware
LanguageEnglish

Related product manuals