Section J - Tracks
Track Maintenance
Track Removal and Replacement
J-6 J-6
9803-9570-4
Track Removal and Replacement
Removing a Track
1 Park the machine on firm and level ground.
2 Using suitable lifting equipment, raise the machine off
the ground. If necessary, place adequate supports
under the undercarriage so that the tracks are clear of
the ground.
3 Release the track tension K
Track
Adjustment ( T J-4).
4 Insert three steel tubes D inside the track, in the
space between the rollers. Rotate the sprocket in
reverse E so that the tubes move with the track and
engage the track tensioning wheel. Exert sideways
force F to slide the track off the track tensioning
wheel.
Fig 4.
Installing a Track
1 Make sure that the machine is safely supported off
the ground before proceeding.
2 Mesh the track links in the sprocket and place the
other end of the track on the track tensioning wheel.
3 Rotate the sprocket in reverse A and pull the track
soles inside the frame.
4 Position the track using a steel tube B and turn the
sprocket again.
5 Make sure track links mesh correctly in the sprocket
and in the track tensioning wheel.
6 Adjust track tension K
Track Adjustment ( T J-4).
7 Raise the machine and carefully remove the
undercarriage supports. Set the machine on the
ground.
Fig 5.
D
E
F
B
A
manualequipospesados@gmail.commanualequipospesados@gmail.com

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the jcb Dumpster HTD5 and is the answer not in the manual?

jcb Dumpster HTD5 Specifications

General IconGeneral
Brandjcb
ModelDumpster HTD5
CategoryConstruction Equipment
LanguageEnglish

Related product manuals