MAINTENANCE SERVICE PROCEDURE
4-47
GREASE EQUALIZER BAR SIDE PIN 4
Greasing points
Grease fitting (1): Front of carrier roller support on left side of
machine
Grease fitting (2): Rear of carrier roller support on right side of
machine
1. Remove all dirt from the top of the track frame and cover.
2. Clean the grease fitting, then supply grease to that fitting
with a grease pump.
REMARK
Supply 3 shots of grease (Operate the grease pump lever 3 times) to each grease fitting, and check that grease is
newly discharged through the seal lip.
If grease is not newly discharged through the lip, continue supplying grease until it is discharged.
GREASE EQUALIZER BAR CENTER PIN 4
(1 place)
1. Open the engine side cover on the left side of the chassis.
2. Clean the grease fitting indicated with the arrow, then sup-
ply grease to that fitting with a grease pump.