Rigging procedures
Adding a pullback with L2-RIGBAR
Type of deployment own array
Rigging accessories L2-RIGBAR
2 Ø19 mm shackles WLL 3.25 t
Min number of operators 2
Horizontal arrays
Do not raise the rear pickup point above the front pickup point.
Pickup points must be aligned with the linking points.
The chains must be as vertical as possible.
With L2-RIGBAR on top With L2-BUMP and L2-BAR on top
Prerequisite
The array is completed and secured under L2-
BUMP with L2-BAR or
See Flying an L2/L2D array with L2-BUMP and L2-BAR (p.60) or
another L2-RIGBAR Flying an L2/L2D array with L2-RIGBAR (p.70).
Procedure
1. Secure L2-RIGBAR on the bottom enclosure using the ball-locking pins.
2. Secure a Ø19 mm shackles WLL 3.25 t to L2-RIGBAR and lift with an additional motor.