Facility Power Considerations Yes No N/A Comment
Does the power frequency meet the
equipment specifications?
Are power outlets available for the new
equipment at the designated location?
Will system power be delivered from
two separate grids?
Is there a UPS to power the equipment?
Do you have the minimum required
power sources to support the power
load for the new hardware? Use
kilowatt (kW) /kilovolt (kVA) to
express power load.
B.6 Power Checklist
Complete the following checklist to ensure that the power requirements are met for
Sun Oracle Database Machine. For information about power requirements, see
Electrical Power Requirements.
Power Checklist Considerations
Yes No N/A Comment
Do you have the minimum required
power sources?
Are power outlets available for the new
equipment at the designated location?
Does the power frequency meet the
equipment specifications?
Is there a UPS to power the equipment?
Is the capacity of the UPS sufficient for
the Exalogic machine?
Does the power source support the
power load for the new hardware? Use
kilowatt (kW)/kilovolt (kVA) to
express power load.
B.7 Safety Checklist
Complete the following checklist to ensure that the safety requirements are met. For
information about safety, see Operational Procedures for Exalogic Machines, and
Temperature and Humidity Requirements.
Safety Checklist Considerations
Yes No N/A Comment
Is there an emergency power shut off?
Power Checklist
B-6 Oracle Exalogic Elastic Cloud Machine Owner's Guide