Chapter 3 Transporting and Installation
HRW Series 3.3 Procedure for Installation
3-11
7. Connect the power cables to the breaker terminal.
Be sure to use a Phillips screwdriver. See Table 3-1 on page 3-7 for recommended torque.
8. Connect the grounding terminal (M8) of
the power cable to the earth bar.
Be sure to use a 13-mm open end wrench.
Recommended torque: 12.5 N•m (9.22 ft-lbf)
[Tips]
See “Table 3-1 Power Cable and Main Breaker (This System)” on page 3-7
for torque value.
9. Attach the breaker cover to the breaker.
10. Attach the front panel.
11. Connect the power cable to the power breaker on customer side (primary side).
Figure 3-8 Connection of Power Cable and Grounding Terminal
Earth bar
Main
breaker
Grounding
terminal
Power cable

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the SMC Networks HRW015-H and is the answer not in the manual?

SMC Networks HRW015-H Specifications

General IconGeneral
BrandSMC Networks
ModelHRW015-H
CategoryChiller
LanguageEnglish

Related product manuals