32
6
Commissioning
6.1 Inspection before Commissioning
No.
Inspection item
Result
1
All cables are intact, well-insulated, and appropriately
dimensioned
2
All cables are connected correctly and firmly
3
The polarity of the power supply cable is correct. The
grounding cable is reliably grounded
6.2 Commissioning Steps
No.
Step
Result
1
Inspection before commissioning
2
Power on the Logger1000.
3
Check whether the indicators of Logger1000 normally flash.
4
Connect the debugging PC to the "ETH" port of the Logger1000
via the network cable (default IP address of "ETH":
12.12.12.12).
Log in the Web at 12.12.12.12 through the IE, Safari or Chrome
browser.
5
Make sure the communication cable connecting the device and
the Logger1000 is firmly in place, and connect the DC circuit
breaker of the inverter to ensure the inverter is supplied with
power.
6
Set serial port parameters by referring to the "7.10.11.1
RS485" chapter, including the baud rate, check bit, data bit, and
stop bit.
The default setting is 9600bps, 8 data bit, 2 stop bit, and no
check bit.

Table of Contents

Other manuals for Sungrow Logger1000A

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Sungrow Logger1000A and is the answer not in the manual?

Sungrow Logger1000A Specifications

General IconGeneral
BrandSungrow
ModelLogger1000A
CategoryData Loggers
LanguageEnglish

Related product manuals