Incoming Inspection
CSA7000 Series, TDS7000 Series, & TDS6000 S eries Instruments User Manual
1-23
e. Run the signal-path compensation routine:
H From the Utilities menu, select Instrument Calibration . . . . This
displays the instrument calibration control window.
H If required because the instrument is in service mode, select the
Signal Path button under Calibration Area.
H Touch the Calibrate button to start the routine.
f. Wait: Signal-path compensation may take five to ten minutes to run.
g. Confirm signal-path compensation returns passed status: Verify that the
word Pass appears in the instrument calibration control window.
2. Return to regular service: Click the Close button to exit the instrument
calibration control window.
Functional Tests
The purpose of these procedures is to confirm that the instrument functions
properly. A list of required test equipment is shown on page 1--21.
NOTE. These procedures verify that the instrument features operate. They do not
verify that they operate w ithin limits.
Therefore, when the instructions in the functional tests that follow call for you to
verify that a signal appears on-screen “that is about five divisions in amplitude”
or “has a period of about six horizontal divisions,” and so forth, do not
interpret the quantities given as limits.