RD 27 Operation
wc_tx000814gb.fm 25
4 Operation
4.1 Preparing the Machine for First Use
Preparing for
first use
To prepare your machine for first use:
1. Make sure all loose packaging materials have been removed from the machine.
2. Check the machine and its components for damage. If there is visible damage,
do not operate the machine! Contact your Wacker Neuson dealer immediately
for assistance.
3. Take inventory of all items included with the machine and verify that all loose
components and fasteners are accounted for.
4. Attach component parts not already attached.
5. Add fluids as needed, including fuel, engine oil, and battery acid.
6. Move the machine to its operating location.
4.2 Position of the Operator
Safe and efficient use of this machine is the operator’s responsibility. Full control of
the machine is not possible unless the operator maintains the proper working
position at all times.
While operating this machine, the operator must:
be seated in the operator’s seat facing forward
wear the seat belt, properly adjusted and latched
have both feet on the control deck
have one hand on the steering wheel at all times
have the other hand free to operate the controls as needed

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Wacker Neuson RD 27-100 and is the answer not in the manual?

Wacker Neuson RD 27-100 Specifications

General IconGeneral
BrandWacker Neuson
ModelRD 27-100
CategoryPower Roller
LanguageEnglish

Related product manuals