Mechanical installation
29
Mechanical installation
What this chapter contains
This chapter contains unpacking instructions, the delivery checklist and the
mechanical installation instructions of the drive.
Unpacking the unit
The drive is delivered in either in a cardboard box or in a plywood package. The
package also contains:
• connection box (only in IP21 units): screws, clamps and vibration dampers (option
+C131)
• box for safety options: ASTO board for the Safe torque off function (option
+Q967) or AGPS board for the Prevention of unexpected start-up function (option
+Q950)
• plastic bag: screws (M3), clamps and cable lugs (2 mm
2
, M3) for grounding the
control cable screens, all manuals (hardware manual, appropriate firmware
manuals and guides, option module manuals), residual voltage warning stickers
and other delivery documents.
The type, size and material of the package depend on the frame size of the drive and
the selected options (see section Package dimensions and weights on page 117).
The following unpacking instructions are examples.
Note: Do not discard any important components that are in the separate cardboard
boxes.