5.1. First startup
At first startup, users have to feed in AC power and switch on the Manual
Switch. Inverter will start up on AC power and LCD display panel will come
live. When the LCD display lighting up, please set Language and Country
according to your needs. After these two items set correctly, LCD display
will enter home page (Figure 5-3). Please make sure “status:” showing no
any error, fault or warning on home page before you feed in DC power.
After DC and AC power are ready, inverter will initially self-test which may
take about 2 minutes and start to feed in power to grid.
5.Turn on/off PV inverter
WARNING ! BURN HAZARD
The enclosure temperature may exceed 70°C while inverter is operation.
A dangerous burn hazard is present in this situation.